Message-ID: <30351274.1075851910059.JavaMail.evans@thyme> Date: Thu, 12 Apr 2001 06:15:00 -0700 (PDT) From: george.robinson@enron.com To: larry.campbell@enron.com Subject: Lockridge Remediation Site Mime-Version: 1.0 Content-Type: text/plain; charset=us-ascii Content-Transfer-Encoding: 7bit X-From: George Robinson X-To: Larry Campbell X-cc: X-bcc: X-Folder: \Larry_Campbell_Nov2001_1\Notes Folders\Lockridge remediation X-Origin: CAMPBELL-L X-FileName: lcampbe.nsf Larry- Remediation efforts to remove PSH have gone well recently and it is now time to focus more attention toward remediation of the dissolved phase plume. This is reflected in the proposed scope. Two files are attached. The first file includes a project scope and cost estimate for 2001. The second file contains photos of the site. The cost estimate is $93,000. This figure includes only contract installation dollars, so the work order amount would be about 20-30% more than this. The bulk of this figure ($53,000) is for system modifications to focus more attention toward remediation of the dissolved phase plume. If you get a chance to look at the photos, be sure to look at the last photo. This photo shows the interior of the SVE knockout box that was installed in Dec 1999 in the NE pit area. This installation has worked very well over the past two winter periods and has greatly increased the effectiveness of the SVE system. The SVE knockout box recently installed at the N Crawar site is nearly identical. Give me a call and lets discuss. -George