X-Folder: \Larry_Campbell_Nov2001_1\Notes Folders\Discussion threads
X-Origin: CAMPBELL-L
X-FileName: lcampbe.nsf

Randy, based upon the records review, this is the only issue that may be a=
=20
problem.  If a tank has been moved to another location, it would trigger=20
requirements which were enacted on the date of the relocation.  For instanc=
e,=20
if a tank constructed prior to 1973 was moved in 1978, there would be=20
emissions control requirements placed on the tank as required by the 1978=
=20
tank regulations.  If the tank had remained at its original location, it=20
would be grandfathered with respect to emissions.  However, because the tan=
k=20
was relocated, it is looked upon as being a tank constructed in 1978 and=20
subject to the 1978 regulations and is no longer grandfathered.

I was not given this information during the records review, so I dont know =
if=20
any of the tanks apply.  If any of the tanks fit into the above scenerio,=
=20
EOTT or Koch will be  looking at some major $$$$$ to bring any subject tank=
=20
into compliance.  Generally speaking, the regualtions and costs to comply=
=20
increase as a function of date.   =20


1. Q. Of the tanks listed on the spreadsheet, have any of the tanks been=20
relocated from its original construction locations?  List the tank, date=20
moved and   location moved to.
A.  Benevides Station Tank 6125 and Mirando Station Tank 28591 were relocat=
ed=20
to those stations.  Three Rivers Tanks 28508 and 28100 were   relocated and=
=20
re-erected at that station.  Duval Station Tank 28052 and Mirando Station=
=20
28045 were relocated and re-erected at those stations prior  to Koch=01,s=
=20
acquisition of those assets.


---------------------- Forwarded by Larry Campbell/ET&S/Enron on 05/09/2001=
=20
10:03 AM ---------------------------
Jim Coen @ EOTT   05/08/2001 10:27 AM

To: Joe Richards/Houston/Eott@Eott, Randy Belyeu/OTS/Enron@ENRON, Larry=20
Campbell/ET&S/Enron@Enron, Warren Fusilier/Remote/Eott@Eott, Jeremy=20
Dawson/Houston/Eott@Eott
cc: =20

Subject: Koch South Texas pipeline data room questions and answers


----- Forwarded by Jim Coen/Houston/Eott on 05/08/2001 10:51 AM -----

=09"Lofing, Michael" <LofingM@kochind.com>
=0905/08/2001 09:48 AM
=09=09=20
=09=09 To: Jim Coen/Houston/Eott@Eott
=09=09 cc:=20
=09=09 Subject: Koch South Texas pipeline data room questions and answers



Jim
Attached are the Koch South Texas Pipeline data room questions with answers
attached.  I have also attached data provided to other bidders.  If you hav=
e
any additional questions, please contact me, 828-4027.
Regards,
Mike


 <<EOTT Questions and Answers_.doc>>  <<over-short labor utilities.xls>>