Lets talk about this tomorrow--obviously this changes the facts somewhat.  DF 
---------------------- Forwarded by Drew Fossum/ET&S/Enron on 01/05/2000 
06:21 PM ---------------------------

01/05/2000 12:34 PM
Louis Soldano
Louis Soldano
Louis Soldano
01/05/2000 12:34 PM
01/05/2000 12:34 PM
To: Michel Nelson/ET&S/Enron@ENRON, Bill Cordes/ET&S/Enron@ENRON, Steven 
Harris/ET&S/Enron@ENRON
cc: Charlie Graham/ET&S/Enron@ENRON, Lorraine Lindberg/ET&S/Enron@ENRON, Drew 
Fossum/ET&S/Enron@ENRON 

Subject: Re: 250 mmcf/d @ Topock  

I am obviously not y2k complaint.   The agreement does read as Charlie 
indicated 

? 2.3  TW shall own, operate and maintain facilities. "...capable of 
delivering no less than 200,000 MMBtu of gas per day..." and PG&E facilities 
"...capable of receiving no less than 200,000 MMBtu per day...".

There are also pressure obligations - a minimum delivery pressure of 600 psig 
and a maximum of 700 psig.   

otherwise, there are no volume restrictions...





Michel Nelson
01/04/2000 10:09 PM
To: Bill Cordes/ET&S/Enron@ENRON, Steven Harris/ET&S/Enron@ENRON, Louis 
Soldano/ET&S/Enron@ENRON
cc:  Graham


Subject: 250 mmcf/d @ Topock

Charlie is doing some more digging, but hasn't found anything in the 
operating agreement to limit us to 250/d yet (other than the July or August 
99 letter related to '250/d limits until all PCB issues are resolved'..
---------------------- Forwarded by Michel Nelson/ET&S/Enron on 01/04/2000 
09:55 PM ---------------------------
   
	
	
	From:  Charlie Graham                           01/04/2000 03:11 PM
	

To: Michel Nelson/ET&S/Enron@ENRON, Donald Vignaroli/ET&S/Enron@ENRON
cc:  

Subject: 250 mmcf/d @ Topock

Mike,

At your request I reviewed the June 27, 1995 Operating Agreement between PG&E 
and TW looking for any volume commitments and found only the following 
reference:

? 2.3  TW shall own, operate and maintain facilities. "...capable of 
delivering no less than 200,000 MMBtu of gas per day..." and PG&E facilities 
"...capable of receiving no less than 200,000 MMBtu per day...".

The Operating Agreement references an Interconnect Agreement between TW and 
PG&E dated 3/16/92.  It does not appear that the Operating Agreement canceled 
or superseded the Interconnect Agreement.  I am trying to find a copy of that 
Interconnect Agreement to see if any quantity language is in it.

Vig, do we have a certificate limit regarding the quantity we can deliver to 
PG&E at Topock?

Charlie