Message-ID: <11529356.1075852428132.JavaMail.evans@thyme>
Date: Thu, 21 Jun 2001 14:32:39 -0700 (PDT)
From: susan.scott@enron.com
To: ron.tapscott@enron.com, rudy.acevedo@enron.com, mike.carson@enron.com, 
	joe.connor@enron.com, david.fairley@enron.com, m..forney@enron.com, 
	l..garcia@enron.com, juan.hernandez@enron.com, 
	rogers.herndon@enron.com, elizabeth.johnston@enron.com, 
	grace.kim@enron.com, heather.kroll@enron.com, 
	gretchen.lotz@enron.com, george.mccormick@enron.com, 
	ron.mcnamara@enron.com, ozzie.pagan@enron.com, 
	laura.podurgiel@enron.com, bill.rust@enron.com, eric.saibi@enron.com, 
	dan.staines@enron.com, jim.terrell@enron.com, 
	joseph.wagner@enron.com, jeffrey.wilson@enron.com
Subject: FW: Entergy/MDEA interconnect update -- corrected
Cc: christi.nicolay@enron.com, donna.fulton@enron.com, sarah.novosel@enron.com, 
	james.steffes@enron.com
Mime-Version: 1.0
Content-Type: text/plain; charset=us-ascii
Content-Transfer-Encoding: quoted-printable
Bcc: christi.nicolay@enron.com, donna.fulton@enron.com, sarah.novosel@enron.com, 
	james.steffes@enron.com
X-From: Scott, Susan </O=ENRON/OU=NA/CN=RECIPIENTS/CN=SSCOTT3>
X-To: Tapscott, Ron </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Rtapsco>, Acevedo, Rudy </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Raceved>, Carson, Mike </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Mcarson2>, Connor, Joe </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Notesaddr/cn=6cf50559-dffc0582-86256946-702acf>, Fairley, David </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Dfairle>, Forney, John M. </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Jforney>, Garcia, Miguel L. </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Mgarcia6>, Hernandez, Juan </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Jhernan3>, Herndon, Rogers </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Rherndo>, Johnston, Elizabeth </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Ejohnst2>, Kim, Grace </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Gkim>, Kroll, Heather </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Hkroll>, Lotz, Gretchen </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Glotz>, Mccormick, George </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Gmccorm>, McNamara, Ron </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Notesaddr/cn=7882b07e-cfe86c34-8625693c-73653e>, Pagan, Ozzie </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Notesaddr/cn=42d0cece-2fe85b00-86256a38-756654>, Podurgiel, Laura </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Lpodurg2>, Rust, Bill </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Brust>, Saibi, Eric </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Esaibi>, Staines, Dan </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Notesaddr/cn=becc1db7-f45f5a-862566d7-6b969d>, Terrell, Jim </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Notesaddr/cn=9318ef04-c26a17e5-882569e7-520d6c>, Wagner, Joseph </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Jwagner2>, Wilson, Jeffrey </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Notesaddr/cn=cd052743-4561eacc-62569f5-54e4bd>
X-cc: Nicolay, Christi </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Notesaddr/cn=5836b2ad-ed2e830f-86256502-7152cc>, Fulton, Donna </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Notesaddr/cn=cde8dae-a0b9ab37-862566b7-7a1609>, Novosel, Sarah </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Notesaddr/cn=e8015336-2d09a27c-862566b9-5830a9>, Steffes, James </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Notesaddr/cn=afb3d0fa-ccb03d20-86256962-56fda5>
X-bcc: 
X-Folder: \JHERNAN3 (Non-Privileged)\Hernandez, Juan\Inbox
X-Origin: HERNANDEZ-J
X-FileName: JHERNAN3 (Non-Privileged).pst


Here is the correct summary -- my apologies for the error.

Entergy Services, Inc.  ER01-1866-000, ER01-1593-000 and ER01-159-001.  Int=
erconnection and Operating Agreement. On March 21, 2001, Entergy Services, =
Inc. files an unexecuted interconnection and operating agreement with the f=
ollowing parties: Mississippi Delta Energy Agency, a joint action agency or=
ganized and existing under the laws of the State of Mississippi, composed o=
f the Clarksdale Public Utilities Commission of the City of Clarksdale, Mis=
sissippi (Clarksdale) and the Public Service Commission of Yazoo City of th=
e City of Yazoo City Mississippi (Yazoo City); Clarksdale; and Yazoo City. =
 On May 29, 2001, FERC accepted and suspended Entergy Services, Inc.'s Marc=
h 21, 2001 agreement -- subject to hearing, settlement discussions, and ref=
und -- to be effective May 1, 2001. FERC accepted the proposed generator im=
balance agreement, to be effective May 1, 2001.  On April 25, 2001, Entergy=
 Services, Inc. (Entergy Services), acting as agent for Entergy Mississippi=
, Inc., submitted an unexecuted network integration transmission service ag=
reement and an unexecuted network operating agreement with 1) Mississippi D=
elta Energy Agency; 2) the City of Clarksdale, Mississippi; and 3) the City=
 of Yazoo City, Mississippi, to be effective as of May 1, 2001.  On June 14=
, FERC issues an order in which it accepts for filing, subject to the outco=
me of an evidentiary hearing and settlement procedures, and suspends for a =
nominal period, an unexecuted Network Integration Transmission Service Agre=
ement (NITSA) and an unexecuted Network Operating Agreement (NOA) between E=
ntergy Services, Inc. (Entergy) and the following entities:  Mississippi De=
lta Energy Agency, the City of Clarksdale, Mississippi and the City of Yazo=
o, Mississippi.  FERC also grants Entergy's request for waiver of the 60-da=
y prior notice requirement to permit the NITSA and NOA to become effective =
May 1, 2001, subject to refund.  Pursuant to Rule 603 of FERC's Rules of Pr=
actice and Procedure, FERC also sets the agreements for hearing, but holds =
the hearing in abeyance pending settlement discussions between the parties.=
  FERC also consolidates Docket No. ER01-1866-000 with Docket Nos. ER01-159=
3-000 and ER01-1593-001.  Request for Rehearing due July 13.
 -----Original Message-----
From: =09Scott, Susan =20
Sent:=09Thursday, June 21, 2001 3:51 PM
To:=09Tapscott, Ron; Acevedo, Rudy; Carson, Mike; Connor, Joe; Fairley, Dav=
id; Forney, John M.; Garcia, Miguel L.; Hernandez, Juan; Herndon, Rogers; J=
ohnston, Elizabeth; Kim, Grace; Kroll, Heather; Lotz, Gretchen; Mccormick, =
George; McNamara, Ron; Pagan, Ozzie; Podurgiel, Laura; Rust, Bill; Saibi, E=
ric; Staines, Dan; Terrell, Jim; Wagner, Joseph; Wilson, Jeffrey
Cc:=09Nicolay, Christi; Novosel, Sarah; Fulton, Donna; Steffes, James
Subject:=09Entergy/MDEA interconnect update

You have probably already received a report of the interconnect agreement d=
escribed below.  The updated portion, describing FERC's order issued last w=
eek, appears in italics.  If you would like more information please let me =
know.

Susan Scott Lindberg
713.853.0596
sscott3@enron.com

***
Commonwealth Edison Company.  ER00-3668-001.  Settlement Issues.  Commonwea=
lth Edison proposed to install equipment at its East Frankfort substation (=
East Frankfort) to accommodate the 138 kV interconnection of University Par=
k's 300 MW peaking generation facility.  Under the agreements, University P=
ark is wholly responsible for the costs of relocating two 345 kV transmissi=
on lines and one 12 kV line at East Frankfort. On November 8, 2000, FERC ac=
cepted and suspended Commonwealth Edison's September 12 agreements, subject=
 to refund and subject to Commonwealth Edison making a compliance filing to=
: 1) set out specific charges for the proposed interconnection of Universit=
y Park's generation facility (together with supporting documentation); and =
2) provide support for the proposed direct assignment of facilities to Univ=
ersity Park.  On June 4, 2000, regarding Commonwealth Edison's revisions to=
 its unexecuted interconnection agreement filed in compliance with FERC's N=
ovember 8 order, FERC: 1) accepted the proposed charge of $900,000 for a T-=
tap connection and $300,000 ($1.2 million) for protective relaying as direc=
tly assignable to University Park; 2) rejected Commonwealth Edison's estima=
ted $9 million for the enhancement of East Frankfort and other changes to t=
he September 12 interconnection agreement not contemplated in the November =
8 order; and 3) rejected Commonwealth Edison's proposed $1.5 million charge=
 related to the line relocation costs, set this matter for hearing, and hel=
d the hearing in abeyance pending settlement discussions between the partie=
s.  On June 12, the Chief Judge issues an order designating a settlement ju=
dge, Judge Jacob Leventhal, and directing him to convene a settlement confe=
rence, to explore the possibility of settlement, to discuss the differences=
 between the parties, and in general to conduct the settlement negotiations=
.  Chief Judge also directs all parties to have persons present at the sett=
lement negotiations with authority to negotiate and accept or approve settl=
ement terms. Chief Judge explains that Judge Leventhal will be available to=
 meet with the parties individually or in groups, in person or by telephone=
 prior to the conference.  Further, he states that a settlement conference =
will convene in a FERC hearing room on June 21, 2001 at 10:00 A.M.