Subject: Cost Estimates - Belen, NM Power Plant
Mime-Version: 1.0
Content-Type: text/plain; charset=us-ascii
Content-Transfer-Encoding: 7bit
X-From: Jeffery Fawcett <Jeffery Fawcett/ET&S/Enron@ENRON>
X-To: Eric Faucheaux <Eric Faucheaux/ET&S/Enron@Enron>
X-cc: 
X-bcc: 
X-Folder: \Kevin_Hyatt_Mar2002\Hyatt, Kevin\Projects
X-Origin: Hyatt-K
X-FileName: khyatt (Non-Privileged).pst

Thanks, Eric.  I'll speak with Steve Rutherford today.





	Eric Faucheaux 02/02/2001 05:43 PM 	

To:	steve@apiweb.com
cc:	Jeffery Fawcett/ET&S/Enron@ENRON, Terry Galassini/ET&S/Enron@ENRON 

Subject:	Cost Estimates - Belen, NM Power Plant

Since time is of the essence for you, Jeffery has requested that I prepare and send an Order of Magnitude Estimate for connection pipelines and measuring facilities for the proposed project.  The estimates include overhead and contingencies but do not include gross up for income taxes.  

Pipelines - $500,000
30"x8" hot tap and 4400 LF of 8" pipeline from TW P/L to measuring facilities/EPNG tie-in
1000 LF of 10" pipeline from measuring facilities/EPNG tie-in to proposed plant site boundry

Measuring Facilities - $550,000
Ultrasonic Measuring facilities and regulating facilities for TW and EPNG pipelines

EPNG Hot-tap and Monitoring Facilities - $200,000
30"x8" hot tap and flow regulation and monitoring equipment

Total Project:  1,250,000 

Futher details may be provided within the weeks to follow that shall include flow schematics, layout plans, sizing details, etc. where time will be permitted.  I may be reached by cellular,713/854-6716, or pager, 887/727-0018, if any questions you may have need to be answered before Monday; otherwise, I can be reached at the office at 713/853-3395.