Message-ID: <14286880.1075860883478.JavaMail.evans@thyme>
Date: Thu, 6 Sep 2001 15:07:40 -0700 (PDT)
From: john.shafer@enron.com
To: eric.gadd@enron.com
Subject: Preliminary Environmental Timeline for Sun Devil Project
Cc: kevin.hyatt@enron.com, larry.campbell@enron.com, doug.cebryk@enron.com, 
	robert.kilmer@enron.com, gina.taylor@enron.com, 
	louis.soldano@enron.com, joe.hartsoe@enron.com
Mime-Version: 1.0
Content-Type: text/plain; charset=us-ascii
Content-Transfer-Encoding: quoted-printable
Bcc: kevin.hyatt@enron.com, larry.campbell@enron.com, doug.cebryk@enron.com, 
	robert.kilmer@enron.com, gina.taylor@enron.com, 
	louis.soldano@enron.com, joe.hartsoe@enron.com
X-From: Shafer, John </O=ENRON/OU=NA/CN=RECIPIENTS/CN=JSHAFER>
X-To: Gadd, Eric </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Egadd>
X-cc: Hyatt, Kevin </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Khyatt>, Campbell, Larry </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Notesaddr/cn=fbf88288-7d541a4a-8625673c-6cab77>, Cebryk, Doug </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Dcebryk>, Kilmer III, Robert </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Rkilmer>, Taylor, Gina </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Gtaylor10>, Soldano, Louis </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Lsoldan>, Hartsoe, Joe </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Jhartso>, 'jschmidt@ENSR.com'
X-bcc: 
X-Folder: \Kevin_Hyatt_Mar2002\Hyatt, Kevin\Projects\Sun Devil
X-Origin: Hyatt-K
X-FileName: khyatt (Non-Privileged).pst

Eric,
As we discussed, with ENSR's assistance I have developed a projected timeli=
ne for developing the FERC required F-1 Exhibit (12 part Resource Reports t=
o satisfy the NEPA requirement) in sufficient detail to meet the FERC filin=
g requirements and expedite the processing of the environmental portion of =
the application.  The aggressive timeline assumes that the expedited FERC "=
Collaborative Approach" will be implemented throughout the processing of th=
e application.  Even with the "Collaborative Approach" and all of the upfro=
nt work done with the environmental community to streamline the processing,=
 the schedule is very, very optimistic and assumes that all conflicting iss=
ues will be resolved quickly and the processing continue. =20

I have requested that Jon Schmidt (ENSR) begin working on a detailed cost e=
stimate, by quarters in two phases.  The first part of the estimate would b=
e to project the environmental cost, by quarters of preparing the 12 Resour=
ce Reports (including the necessary field work) that would get Sun Devil to=
 an FERC filing in the first quarter of 2002 that would not be rejected.  T=
he second component of the cost estimate would be to complete the field wor=
k and permitting phases during the processing of the application.  This inc=
ludes participating in FERC scoping meetings and agency meetings as require=
d.  This would include assisting the third party environmental contractor i=
n working on the EIS to expedite the writing as needed.  It would also incl=
ude mitigation packages to satisfy agency requirements.  The third and fina=
l component would be to budget for a Third Party Environmental Contractor t=
o write the EIS document during the time that the field work is being devel=
oped and to process the same with the FERC Staff.  Once we get the "White P=
aper" Fatal Flaw analysis that ENSR is preparing for this project we will h=
ave enough information along with the budget to get us to the FERC filing t=
o make some quantifiable decisions on moving forward when comparing those t=
o the commercial advantages that you are developing.

If you have any questions, please give me a call.  John Shafer
