Message-ID: <19588921.1075840997621.JavaMail.evans@thyme>
Date: Fri, 30 Mar 2001 03:26:00 -0800 (PST)
From: bill.iii@enron.com
To: portland.shift@enron.com
Subject: Length off-peak at Palo Verde
Cc: ryan.slinger@enron.com, bert.meyers@enron.com, leaf.harasin@enron.com, 
	eric.linder@enron.com
Mime-Version: 1.0
Content-Type: text/plain; charset=us-ascii
Content-Transfer-Encoding: 7bit
Bcc: ryan.slinger@enron.com, bert.meyers@enron.com, leaf.harasin@enron.com, 
	eric.linder@enron.com
X-From: Bill Williams III
X-To: Portland Shift
X-cc: Ryan Slinger, Bert Meyers, Leaf Harasin, Eric Linder
X-bcc: 
X-Folder: \eric linder 6-28-02\Notes Folders\All documents
X-Origin: LINDER-E
X-FileName: eric linder 6-28-02.nsf

We have length at PV all day on Sunday, and light load on Monday.  That is HE 
2-24 MST on Sunday, and HE1-6,23,24 on Monday.  The energy is parked with PNM 
at PV.  The cost is $125.  We are long in position manager.  Please route the 
sale to buy/resale #566175, and then make the sale under the ST-WBOM book.  
There is no HE 3 in Pacific time.  This may require some creativity on your 
part.   Please call me with any questions and good luck!

Bill