Message-ID: <31753364.1075844138093.JavaMail.evans@thyme>
Date: Thu, 11 Jan 2001 01:39:00 -0800 (PST)
From: lorna.brennan@enron.com
To: steven.harris@enron.com, jeffery.fawcett@enron.com, 
	lorraine.lindberg@enron.com, kevin.hyatt@enron.com, 
	tk.lohman@enron.com, michelle.lokay@enron.com, 
	lindy.donoho@enron.com, jeffery.fawcett@enron.com, 
	jo.williams@enron.com
Subject: El Paso Maintenance - Opportunity?
Mime-Version: 1.0
Content-Type: text/plain; charset=us-ascii
Content-Transfer-Encoding: 7bit
X-From: Lorna Brennan
X-To: Steven Harris, Jeffery Fawcett, Lorraine Lindberg, Kevin Hyatt, TK Lohman, Michelle Lokay, Lindy Donoho, Jeffery Fawcett, Jo Williams
X-cc: 
X-bcc: 
X-Folder: \Michelle_Lokay_Dec2000_June2001_2\Notes Folders\All documents
X-Origin: LOKAY-M
X-FileName: mlokay.nsf

El Paso has postponed Line 1300 and Line 1301 maintenance projects on the San 
Juan Crossover until February. Flagstaff Station and the Navajo 2D turbine 
will be down Jan. 22-23, cutting North Mainline capacity by 50 MMcf/d. One 
Rio Vista turbine will be down Jan. 22-25, limiting capacity of the IEXCPT37 
and IGCNMX37 interconnects to a total of 125 MMcf/d.