Subject: Re: VEPCO files Interconnection Proc. at FERC
Mime-Version: 1.0
Content-Type: text/plain; charset=us-ascii
Content-Transfer-Encoding: 7bit
X-From: Kay Mann
X-To: Reagan Rorschach
X-cc: 
X-bcc: 
X-Folder: \Kay_Mann_June2001_4\Notes Folders\'sent mail
X-Origin: MANN-K
X-FileName: kmann.nsf

---------------------- Forwarded by Kay Mann/Corp/Enron on 11/09/2000 09:06 
AM ---------------------------


Christi L Nicolay@ECT
11/07/2000 01:19 PM
To: Ozzie Pagan/HOU/ECT@ECT
cc: Heather Kroll/HOU/ECT@ECT, Bob Carter/HOU/ECT@ECT, Barbara N 
Gray/HOU/ECT@ECT, Lloyd Will/HOU/ECT@ECT, Mitch Robinson/Corp/Enron@Enron, 
Patrick Hanse/HOU/ECT@ECT, Ben Jacoby/HOU/ECT@ECT, Barton Clark/HOU/ECT@ECT, 
Kay Mann/Corp/Enron@Enron, Larry Soderquist/HOU/ECT@ECT, Bill 
Rust/HOU/ECT@ECT, James D Steffes/NA/Enron@Enron, Richard 
Shapiro/NA/Enron@Enron, Sarah Novosel/Corp/Enron@ENRON, Joe 
Hartsoe/Corp/Enron@ENRON, Donna Fulton/Corp/Enron@ENRON, Mary 
Hain/HOU/ECT@ECT 

Subject: Re: VEPCO files Interconnection Proc. at FERC  

FYI.  The VEPCO attorney said that currently VEPCO is taking about 60 days 
each for the System Impact Study and the Facilities Study.  Because of the 
increase in study requests, VEPCO is filing for 90 days for Fac. Studies, 
below.


   
	
	
	From:  Christi L Nicolay                           11/06/2000 02:29 PM
	

To: Ozzie Pagan/HOU/ECT@ECT, Heather Kroll/HOU/ECT@ECT, Bob 
Carter/HOU/ECT@ECT, Barbara N Gray/HOU/ECT@ECT, Lloyd Will/HOU/ECT@ECT, Mitch 
Robinson/Corp/Enron@Enron, Patrick Hanse/HOU/ECT@ECT, Ben Jacoby/HOU/ECT@ECT, 
Barton Clark/HOU/ECT@ECT, Kay Mann/Corp/Enron@Enron, Larry 
Soderquist/HOU/ECT@ECT, Bill Rust/HOU/ECT@ECT, James D 
Steffes/NA/Enron@Enron, Richard Shapiro/NA/Enron@Enron, Sarah 
Novosel/Corp/Enron@ENRON, Joe Hartsoe/Corp/Enron@ENRON, Donna 
Fulton/Corp/Enron@ENRON, Mary Hain/HOU/ECT@ECT
cc:  

Subject: VEPCO files Interconnection Proc. at FERC

On 10/27/00, VEPCO filed interconnection procedures at FERC (Docket No. 
ER01-247)(Protests due 11/17/00).  These largely mirror CP&L's 
interconnection procedures that were recently approved by FERC.  Therefore, I 
do not think that Enron should protest or intervene.

Customer is required to pay for the cost of a new system impact/facilities 
study if the study information/interconnection/upgrade costs change due to a 
customer higher in the queue losing its queue spot.
System impact studies should take 60 days or less.  Facilities studies should 
take 90 days or less.