Message-ID: <28560838.1075845779959.JavaMail.evans@thyme>
Date: Fri, 27 Oct 2000 00:39:00 -0700 (PDT)
From: scott.healy@enron.com
To: jeffery.ader@enron.com, heather.kroll@enron.com, stephen.plauche@enron.com, 
	kay.mann@enron.com
Subject: Revision No.1 for ENA Fuelcell Estimate dated 10/26/2000
Mime-Version: 1.0
Content-Type: text/plain; charset=us-ascii
Content-Transfer-Encoding: 7bit
X-From: Scott Healy
X-To: Jeffery Ader, Heather Kroll, Stephen Plauche, Kay Mann
X-cc: 
X-bcc: 
X-Folder: \Kay_Mann_June2001_2\Notes Folders\Discussion threads
X-Origin: MANN-K
X-FileName: kmann.nsf

FYI.

---------------------- Forwarded by Scott Healy/HOU/ECT on 10/27/2000 07:40 
AM ---------------------------


Michael D Nanny@ENRON_DEVELOPMENT
10/26/2000 04:33 PM
To: Scott Healy/HOU/ECT@ECT, Stephen Plauche/Corp/Enron@Enron
cc: Robert P Virgo/HOU/ECT@ECT 
Subject: Revision No.1 for ENA Fuelcell Estimate dated 10/26/2000


---------------------- Forwarded by Michael D Nanny/ENRON_DEVELOPMENT on 
10/26/2000 04:25 PM ---------------------------


Ray Danner@ENRON
10/26/2000 03:44 PM
To: Michael D Nanny/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT, Mike 
Coleman/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT, Terri 
Austin/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT
cc: Jay Patel/ENRON_DEVELOPMENT@ENRON_DEVELOPMENt, Robin Long/NA/Enron@ENRON 
Subject: Revision No.1 for ENA Fuelcell Estimate dated 10/26/2000

Mike, 

Attached are the revised (Revision 1) BOP Estimates for the Wallingford Fuel 
Cells Power Project (10 cells - 21.2 MW) and the Midcon (Hartford) Fuel Cells 
Power Project (12 cells - 28.8 MW) in the amount of $9.5MM and $9.6 MM 
respectively. These estimates reflect our discussions today with the 
following comments provided:

 1. I have lowered the Contingency to 10% from 15% per the direction from 
Mike Coleman. Estimating does not agree with this reduced contingency and I  
feel it is inadequate for the level of detail provided.  

 2. Because of this reduction in contingency, I have re-evaluated the 
concrete account and moved the Slab on Grade from the FCE Scope to the EE&CC  
Scope of Work. I have also revised the foundations for FCE based on the 
quantities they provided. 

 3. We are using $10,000 per cell for Grounding Grid based on reviewing 
additional estimating data. (The earlier number of $75,000 for the first two 
(2) cells  and $25,000 for each additional cell was provided as an estimate 
from FCE.  We agree it is too high.

 4. Based on our discussions, we are using $450,000 per project for 
Engineering Services.

A Basis of Estimate is also provided.  

Please call if you have questions or if you want to have additional meetings.

Ray Danner

---------------------- Forwarded by Ray Danner/NA/Enron on 10/26/2000 03:26 
PM ---------------------------
From: Jay Patel@ENRON_DEVELOPMENT on 10/26/2000 03:24 PM
To: Ray Danner/NA/Enron@Enron
cc:  

Subject: Revision No.1 for ENA Fuelcell Estimate dated 10/26/2000

Ray, herewith, please find the subject Estimate and respective Basis of 
Estimate.

                        

Regards
Jay N. Patel
   X-55262  