Message-ID: <6645251.1075845894812.JavaMail.evans@thyme>
Date: Mon, 11 Dec 2000 10:46:00 -0800 (PST)
From: lee.johnson@ss.ps.ge.com
To: rebecca.walker@enron.com, lee.johnson@ss.ps.ge.com
Subject: RE: LM 6000 Breakout Contract Amounts
Cc: kay.mann@enron.com, ben.jacoby@enron.com, pthompson@akllp.com, 
	ccobb@akllp.com
Mime-Version: 1.0
Content-Type: text/plain; charset=us-ascii
Content-Transfer-Encoding: 7bit
Bcc: kay.mann@enron.com, ben.jacoby@enron.com, pthompson@akllp.com, 
	ccobb@akllp.com
X-From: lee.johnson@ss.ps.ge.com
X-To: Rebecca.Walker@enron.com, lee.johnson@ss.ps.ge.com
X-cc: Kay.Mann@enron.com, Ben.Jacoby@enron.com, pthompson@akllp.com, ccobb@akllp.com
X-bcc: 
X-Folder: \Kay_Mann_June2001_3\Notes Folders\Lm6000
X-Origin: MANN-K
X-FileName: kmann.nsf

Rebecca,

John Ayres and I met today.  He wishes to add the interconnect piping
between the chiller and cooling tower options in Exhibit N-2 for the ESA
Electrobolt Project.  This adds a total of $ 266,400 to the Jan 15, 2001
payment (equal to $ 33,280 per unit).  There will be no effect on the
12/27/00 payment amount.  I've edited your spread sheet to show this.

John Ayres asked if he could have a stripped down version of the Spread
sheet showing only the ESA amounts.

Kay, You'll notice that the Cooling Tower Option is Exhibit N-2 was changed
to add this interconnect piping to the scope.

I hope this helps.

Regards,

Lee
-----Original Message-----
From: Rebecca.Walker@enron.com [mailto:Rebecca.Walker@enron.com]
Sent: Friday, December 08, 2000 9:30 AM
To: lee.johnson@ss.ps.ge.com
Cc: Kay.Mann@enron.com; Ben.Jacoby@enron.com; pthompson@akllp.com;
ccobb@akllp.com
Subject: LM 6000 Breakout Contract Amounts


Attatched please find a contract payment summary for the LM 6000 turbines.

(See attached file: LM 6000 Breakout Contracts.xls)

Feel free to contact me with any questions.

Rebecca Walker
713-345-7968


 - Paymentschedule_LM 6000 Breakout Contracts_121100edits for 
ESAchillerpiping.xls