For your review.
---------------------- Forwarded by Kay Mann/Corp/Enron on 01/17/2001 02:27 
PM ---------------------------


"Thompson, Peter J." <peterthompson@akllp.com> on 01/17/2001 02:24:47 PM
To: "Alan. Larsen (E-mail)" <Alan.Larsen@enron.com>, "Kay Mann (E-mail)" 
<kay.mann@enron.com>, "Kent. Shoemaker (E-mail)" <kent.shoemaker@ae.ge.com>, 
"Lee. Johnson (E-mail)" <lee.johnson@ss.ps.ge.com>, "Sheila Tweed (E-mail)" 
<Sheila.Tweed@enron.com>
cc: "Pipitone, Paul" <paulpipitone@akllp.com>, "Cobb, Chris" 
<chriscobb@akllp.com> 

Subject: Fountain Valley/GE Facility Agreement



 Attached please find the latest draft of the Fountain Valley/GE
Facility Agreement (the second document attached below), as well as a
blackline showing changes to the original form agreed to with GE.  This
revised draft incorporates (a) all of Lee's comments but for his
comments on Section 10.6 and Exhibit B - 550 psig (for which I am still
awaiting confirmation), (b) Kay's comments on Exhibit S and (c) John
Rigby's comments.  To complete we will need to insert the date the
agreement is signed, confirm the specific performance guarantees and the
items in (a) above, and insert Exhibit H-2 manually.  I will be out of
the office for the remainder of the day.  In my absence, please contact
Chris Cobb at (202) 662-3016.
 <<CRO- Fountain Valley GE/Facility Agmt -Original Form vs. Version
8.DOC>>  <<Fountain Valley GE/Turbine Agreement - Version 8.DOC>> 
 - Facility Agmt -Original Form vs. Version 8.DOC
 - Turbine Agreement - Version 8.DOC