Message-ID: <4595499.1075842602681.JavaMail.evans@thyme>
Date: Mon, 24 Jul 2000 08:42:00 -0700 (PDT)
From: dan.bump@enron.com
To: scott.josey@enron.com, brian.redmond@enron.com
Subject: Crescendo Energy weekly meeting 07/25
Cc: gerald.nemec@enron.com
Mime-Version: 1.0
Content-Type: text/plain; charset=us-ascii
Content-Transfer-Encoding: 7bit
Bcc: gerald.nemec@enron.com
X-From: Dan J Bump
X-To: Scott Josey, Brian Redmond
X-cc: Gerald Nemec
X-bcc: 
X-Folder: \Gerald_Nemec_Dec2000_June2001_1\Notes Folders\All documents
X-Origin: NEMEC-G
X-FileName: gnemec.nsf

Gentlemen:

I will be on the road tomorrow in meetings related to Project 20/20 and 
therefore will miss our weekly meeting.  However, the following list provides 
a general summary of issues/events:

1)  Legal has prepared a draft of the letter to Wildhorse detailing our 
acquisition of Enogex's reserves and the associated gathering contract; 
Gerald's looking for comments regarding the current issues with the contract 
(dedication, quality, pressure, etc.).  I hope we can get the letter to 
Wildhorse ASAP.

By the way, NG/Crescendo has approved Gerald's letter allowing ENA to 
negotiate with Wildhorse et al on Crescendo's behalf.

2)  I have scheduled a meeting with Wildhorse on Aug. 1 & 2 to get a field 
tour of the Wildhorse assets in this area and get a better understanding of 
our gathering & processing options.  I'll coordinate with Rusty to see who, 
if anyone, from Houston will attend; I suggest they fly directly to Grand 
Junction, CO on Tues morning.  I anticipate that Dan Reineke, Crescendo's 
contract operator who has a significant history in this area, will be in 
attendance also.

3)  Wildhorse was in the field last week identifying long-term solutions to 
improve current production, as well as preparing cost estimates for the low 
Btu gas.  They've said this since late June, however, they hope to have a 
proposal within two weeks.  I told them that's too long.  Maybe the letter 
above will help.

4)  Continuing to work on a meeting schedule with Tom Brown....this is a 
priority.  Plan to have follow-up meetings with other 3rd party producers 
possibly next week while in Grand Junction and the following week at the COGA 
Conference (Colorado O&G Ass'n) in Denver.

5)  Working with Legal to get a draft processing agreement and gas purchasing 
structure prepared for the above potential 3rd party producers.

6)  Lastly, Wildhorse told me today that they have repaired a propane unit at 
a plant in the San Arroyo area (Westwater) which they think will allow some 
gas deliveries to resume into NWPL from Westwater.  Bottom-line:  Wildhorse 
says this should increase volumes from our wells in San Arroyo as early as 
tomorrow.   We'll see; at least they seem to be trying to resolve some 
production problems which will help us get more comfortable transacting the 
VPP.