Message-ID: <18898103.1075842591247.JavaMail.evans@thyme>
Date: Wed, 3 May 2000 09:53:00 -0700 (PDT)
From: gerald.nemec@enron.com
To: ron.tapscott@enron.com, scott.monson@enron.com
Subject: Mooring Facility Construction
Cc: steve.hooser@enron.com
Mime-Version: 1.0
Content-Type: text/plain; charset=us-ascii
Content-Transfer-Encoding: 7bit
Bcc: steve.hooser@enron.com
X-From: Gerald Nemec
X-To: Ron Tapscott, Scott A Monson
X-cc: Steve Van Hooser
X-bcc: 
X-Folder: \Gerald_Nemec_Dec2000_June2001_1\Notes Folders\All documents
X-Origin: NEMEC-G
X-FileName: gnemec.nsf

Attached is a draft of the turnkey construction contract for your review.  

Ron,  As we discussed, Exhibit A - Scope of Work will need to be included.  
Please note the following points:

1.  Liquidated Damages - Need to assess a value for these damages.
2.  Force Majeure - This would currently provide EE&CC with relief from the 
In-Service Date requirements and consequently, the LDs.  Is this acceptable?
3.  Permitting - Need to specify in Exhibit F, those permits that ENA would 
secure, and make EE&CC responsible for any others.
4.  Utility Coordination - Currently this is very generally.  Are there 
specific responsibilities that should be stated in this Agreement wrt the 
Utility?

Please review with these in mind.  I will be out tommorrow and Friday.  Let's 
plan on meeting Monday to discuss the draft.  