Message-ID: <18926939.1075857217054.JavaMail.evans@thyme>
Date: Tue, 31 Oct 2000 05:53:00 -0800 (PST)
From: chris.meyer@enron.com
To: fred.mitro@enron.com
Subject: Re: Excelon questions - Lincoln
Cc: don.miller@enron.com, ross.newlin@enron.com, stuart.zisman@enron.com, 
	benjamin.rogers@enron.com
Mime-Version: 1.0
Content-Type: text/plain; charset=us-ascii
Content-Transfer-Encoding: 7bit
Bcc: don.miller@enron.com, ross.newlin@enron.com, stuart.zisman@enron.com, 
	benjamin.rogers@enron.com
X-From: Chris Meyer
X-To: Fred Mitro
X-cc: Don Miller, Ross Newlin, Stuart Zisman, Benjamin Rogers
X-bcc: 
X-Folder: \Benjamin_Rogers_Dec2000_2\Notes Folders\Discussion threads
X-Origin: Rogers-B
X-FileName: brogers.nsf

 Please confirm my opinion with Stuart/Chris Meyer to make sure that we have 
not granted any interconnection rights to Northern Border/Peoples.

We have not granted any interconnection rights to Northern Border/Peoples.







Fred Mitro
10/31/2000 01:41 PM
To: Don Miller/HOU/ECT@ECT
cc: Ross Newlin/HOU/EES@EES, Stuart Zisman/HOU/ECT@ECT, Benjamin 
Rogers/HOU/ECT@ECT, Chris Meyer/HOU/ECT@ECT, Ross Newlin/HOU/EES@EES 
Subject: Excelon questions - Lincoln

Don:

The questions that I was unable to answer for Excelon (PECO) during the 
Lincoln site visit are as follows:

1.  What is the gas consumption per unit during start-up?

2.  What is the reference # for the 2nd ComEd Interconnection Feasibility 
Study?  Is this document on deal bench?

3.  Do any other parties have a right to interconnect to the Project's gas 
pipeline lateral?


My input to these questions is:

1.  None.  I am not familiar with this area.

2.  I saw this 2nd study is out on deal bench at least a week ago.  As long 
as it wasn't removed, it should be there.   I do not know the reference #.

3.  I do not believe that any other parties have a right to connect to the 
gas lateral owned by Des Plaines LLC.  (In fact,  I believe that we are 
statutorily prevented from supplying gas to other end users - Des Plaines LLC 
is neither an interstate pipeline nor a gas LDC).  Please confirm my opinion 
with Stuart/Chris Meyer to make sure that we have not granted any 
interconnection rights to Northern Border/Peoples.

Call me to discuss.

Fred