Subject: GTV weekly status update
Mime-Version: 1.0
Content-Type: text/plain; charset=ANSI_X3.4-1968
Content-Transfer-Encoding: 7bit
X-From: Wei, Zhiyong </O=ENRON/OU=NA/CN=RECIPIENTS/CN=ZWEI>
X-To: Kitchen, Louise </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Notesaddr/cn=e5cf97bb-467b6eef-8625687a-893a0>, Storey, Geoff </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Gstorey>, Sullivan, Colleen </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Notesaddr/cn=6e1bba0e-fff2c76b-8625654c-6c6305>, Bibi, Philippe A. </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Pbibi>, Perlman, Beth </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Bperlman>, Stock, Stephen </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Sstock>
X-cc: 
X-bcc: 
X-Folder: \Storey, Geoff\Storey, Geoff\IT
X-Origin: STOREY-G
X-FileName: Storey, Geoff.pst

Please see below for the weekly status report for the GTV project and please see the attached file for the updated project timeline.

GTV status meeting attendees:  Zhiyong Wei, Russ Severson, Francis Lim, Jeremy Wong, Bill Fortney, Chuck Ames, Geoff Storey, Karima Husain, Jay Krish, Mike Swaim, Nayan Dattani, George Grant, Narasim Kasaru.

Accomplishments:
?	Incorporating physcial deal positions in TDS:
o	Changes for the view aggregation have been completed.
o	Expandable Total in Cash Position on schedule (please see the attached project timeline).

?	Single point of deal entry for term deals:
o	Phase 1 of single point of deal entry for term deals is in user test.

?	Gas Daily deals:
o	Revisions for changes to PortCalc application to create GDI calc in ERMS have been worked on.

?	Live feeds for Gas Daily/intra-month curves:
o	Released to production.

?	Option Grid (phase 2):
o	Released to production.

?	Gas Daily options (phase 2):
o	Changes to PortCalc application have been completed and in user test.
o	The Option Delta Change Forward Month report has been completed and in user test.

?	Basis Options (phase 2):
o	Development of deal entry type for Basis Options complete in TAGG.

Plans for the week ending 5/25/01:
?	Continue IT development of Phase I items.
o	Changes to PortCalc for valuing physical outer month positions.
o	Some modification to GDI Calc.
o	Changes to curve shift report for GDI Calc.
o	Expandable Total in Cash Position.

?	Continue IT development of Phase II issues.

Issues / Open Items:
None

 
Thanks

Zhiyong