Message-ID: <84253.1075860907048.JavaMail.evans@thyme>
Date: Tue, 12 Mar 2002 08:25:02 -0800 (PST)
From: jeff.whippo@enron.com
To: ben.asante@enron.com, team.san-juan@enron.com, rich.jolly@enron.com, 
	david.roensch@enron.com, darrell.schoolcraft@enron.com
Subject: RE: San Juan Pigging/DRA
Cc: dan.pribble@enron.com, r..keller@enron.com, kimberly.watson@enron.com, 
	ron.matthews@enron.com
Mime-Version: 1.0
Content-Type: text/plain; charset=us-ascii
Content-Transfer-Encoding: 7bit
Bcc: dan.pribble@enron.com, r..keller@enron.com, kimberly.watson@enron.com, 
	ron.matthews@enron.com
X-From: Whippo, Jeff </O=ENRON/OU=NA/CN=RECIPIENTS/CN=JWHIPPO>
X-To: Asante, Ben </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Basante>, San-Juan, Team </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Notesaddr/cn=21560c05-6fdcfa13-86256745-4aaf>, Jolly, Rich </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Rjolly>, Roensch, David </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Notesaddr/cn=68f10420-593507c0-86256744-5ee2d3>, Schoolcraft, Darrell </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Dschool>
X-cc: Pribble, Dan </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Dpribbl>, Keller, John R. </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Jkeller3>, Watson, Kimberly </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Kwatson>, Matthews, Ron </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Rmatthe>
X-bcc: 
X-Folder: \Kim_Watson_Mar2002\Watson, Kimberly\E-mail Bin
X-Origin: Watson-K
X-FileName: kwatson (Non-Privileged).pst

San Juan Team,

Do you have a pig run scheduled in the next day or two?

Jeff

 -----Original Message-----
From: 	Asante, Ben  
Sent:	Monday, March 11, 2002 3:29 PM
To:	San-Juan, Team; Jolly, Rich; Roensch, David; Whippo, Jeff; Schoolcraft, Darrell
Cc:	Pribble, Dan; Keller, John R.; Watson, Kimberly; Matthews, Ron
Subject:	RE: San Juan Pigging/DRA

I am attaching a profile of the efficiencies between Bloomfield and Bisti for Feb 22-
March 11.

 << File: sj3.doc >> 
Summary
1)	Before pigging, (i.e. 21-27th), the efficiency was about 96.5%
2)	After the pig run on the 27th, the efficiency increased to about 102% for two days.
3)	It averaged about 101% for the next 6 days (i.e. 28th-5th March).  
4)	It then steadily plummeted to 98% over a 3-day period - a percent degradation a day! (5th-8th March)
5)	It remains around the 98% average today.

Essentially, the high efficiency resulting from the 27th Feb pigging lasted just about a week.
The targeted efficiency for this section is 103%.

At the TW commercial meeting this afternoon, we indicated that applying the DRA around the end of May (together with other planned outages) may be the way to go. Meanwhile,  I believe we should schedule another pig run as soon as we can. 
I did also receive the sample collected from the last pig run. I will have it analyzed and report on our findings.

Please let me know any thoughts you may have on this issue

ben

Original Message-----
From: 	San-Juan, Team  
Sent:	Wednesday, February 27, 2002 3:04 PM
To:	Asante, Ben; Jolly, Rich; Roensch, David; Whippo, Jeff; Schoolcraft, Darrell
Subject:	San Juan Pigging

We kicked a pig down the San Juan Lat. on 2-27-02 @ 08:03 MST Pressure was 1145 PSI, Flow of 840.  It was a newly rebuild pig and was kicked dry.   Bisti was down for 55 min, and the pig went by Bisti @ 10:26 MST.  Data at each valve site retreved off RTUs.   If you have any questions or comments, please call.
                              
                                                                                                             Thanks,     -Brian-