Subject: TW Capacity Affected for Red Rock Tie-ins
Cc: byron.rance@enron.com, l..eisenstein@enron.com, morgan.gottsponer@enron.com, 
	ben.asante@enron.com, darrell.schoolcraft@enron.com, 
	jerry.graves@enron.com, rich.jolly@enron.com, earl.chanley@enron.com
Mime-Version: 1.0
Content-Type: text/plain; charset=us-ascii
Content-Transfer-Encoding: quoted-printable
Bcc: byron.rance@enron.com, l..eisenstein@enron.com, morgan.gottsponer@enron.com, 
	ben.asante@enron.com, darrell.schoolcraft@enron.com, 
	jerry.graves@enron.com, rich.jolly@enron.com, earl.chanley@enron.com
X-From: Faucheaux, Eric </O=ENRON/OU=NA/CN=RECIPIENTS/CN=EFAUCHEA>
X-To: Centilli, James </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Notesaddr/cn=38d4c597-37303352-862566b7-511cd0>, Watson, Kimberly </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Kwatson>, Lindberg, Lorraine </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Llindbe>
X-cc: Rance, Byron </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Brance>, Eisenstein, Arnold L. </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Aeisens>, Gottsponer, Morgan </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Mgottsp>, Asante, Ben </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Basante>, Schoolcraft, Darrell </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Dschool>, Graves, Jerry </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Jgraves>, Jolly, Rich </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Notesaddr/cn=55eee558-76f46491-86256743-7d2b01>, Chanley, Earl </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Echanley>
X-bcc: 
X-Folder: \KWATSON (Non-Privileged)\Watson, Kimberly\Inbox
X-Origin: Watson-K
X-FileName: KWATSON (Non-Privileged).pst

The following volumes are capacities west of Station 1 that will result fro=
m tie-in construction work slated for the Red Rock expansion.  Tie-in assem=
blies will be required on both the Mainline and Loopline at stations 1, 2, =
and 3.  New block and side valve assemblies for new compressor and scrubber=
s will be installed on the suction side main and loop lines at each station=
.  The tie-in will entail blocking (isolating) a line segment within the st=
ation yard on the suction side (each line done separately) thus creating a =
dead leg back to the next upstream block valve crossover(s).  Hence, all of=
 the flow will be forced into a single line when making tie-in on the adjac=
ent pipeline line.  The result of forcing all volumes into a single line wi=
ll produce greater pressure losses in the operating segment to the existing=
 compression and reduce throughput due to lower suction pressure and respec=
tive horsepower limitations.  Discharge piping at the station having tie-in=
 work will be unchanged regarding valving configurations.

Tie-in=09Schedule/Duration=09Capacity=09X-over Status
CS 2 ML=09Oct '01 / 4 days=09960 MMcfd=09MLV 3010-open us/ds x-over; open u=
s 30" x-over
CS 2 LL =09Oct '01 / 2 days=09960 MMcfd=09MLV 3010-open us/ds x-over, open =
us 30" x-over
CS 1 ML=09Mar '02=09/ 4 days=09990 MMcfd=09MLV 2012 & 2011-open us/ds x-ove=
r; open us 30" x-over
CS 1 LL=09Mar '02=09/ 2 days=09990 MMcfd=09MLV 2012 & 2011-open us/ds x-ove=
r; open us 30" x-over
CS 3 ML=09Apr '02=09/ 4 days=091010 MMcfd=09MLV 4012 & 4011-open us/ds x-ov=
er; open us 30" x-over
CS 3 LL=09Apr '02=09/ 2 days=091010 MMcfd=09MLV 4012 & 4011-open us/ds x-ov=
er; open us 30"x-over

Notes:
1.=09Specific schedule dates are forthcoming
2.=09Schedules could be impacted by material deliveries and is based upon r=
eceipt of construction permits
3.=09Durations consider working around the clock until completed